Spar Installation
With the doors more or
less complete, it was time to move on to something else. Why not install
the spar? The only
thing holding me back was the idea that I would have to relinquish 100% of the
garage space to the airplane, and park my car outside. Or would I?
With some strategic planning, perhaps I would still be able to both vehicles in
there. So I took some measurements and built an AutoCAD drawing. I
found that moving my bowling-alley-work-bench into the corner, and putting the
fuselage at an angle would still allow me to fit the car in there, although it
was pretty tight. So I had my friend Brad come over and help me position
the fuselage on the leveling jig in a pre-measured
location. What a deal... I bought myself a few more months of getting into
a warm, dry car in the mornings.
 Alrighty
then... time to break out the sabre saw again and
do some more cutting. There's something a little disturbing about cutting
big chunks out of one's nifty fuselage, but it was necessary. The spar
fits into these "slots." In the far left photo, you can see the
NACA inlet in place. Actually it was just resting there when I took the
photo. It gets installed later.
You've probably heard the
expression "measure twice, cut once." Well, when it comes to
positioning the spar in place, I altered the phase somewhat: my version is
"measure 66 times, glue once." It's kind of important that the
spar go in level and normal. I used water levels, digital levels, tape
measures and plumb bobs to make sure everything was groovy before mixing up the
flox. The fuselage was leveled on the leveling jig, and the spar supported
and shimmed on saw horses.
Once I was satisfied with
the spar alignment, I mixed up some flox and bonded the thing in place.
That was followed by 2 plies of S2 glass around all the joints, both inside and
outside the fuselage. And there you have it... one spar installation.

A little later (after the
firewall and NACA Scoop
had been installed) it was time to cut out the spar center sections. This
is done to allow access for systems installations (hydraulic lines & electrical
components) later. Pretty easy work using a hole saw and sabre
saw, but when I removed the panels I found a problem: The inside face
of this panel was bare core. I was expecting to see fiberglass in
there. "This could be bad" I thought, so I called the
factory. Indeed,
their first response was "we'll send you a new spar." Huh?
A nice gesture considering it's a $4,000 part, but good grief, removing the spar
at this stage would be highly destructive to my fuselage and firewall. In
actuality the panel did have the correct number of plies installed, it's just
that they were all on the forward side of the core with none on the aft side.
I needed to try and fix
this thing in place. But how? The missing plies extended from
centerline to 40 inches outboard in each direction. Even with my nifty new
cutouts I couldn't reach that far outboard.
My
solution: Cut two additional access holes mid-spar (1 per side) to allow
me to get my hands in there. It was difficult using mirrors and working
around corners, but I managed to get the area cleaned and prepped, and 2 plies
of S2 glass layed up in all missing areas. I put 2 additional plies inside
to strengthen the access holes, and once the access panels are bonded back in
place, I'll put 3 more plies over the outside. Not only is strength
critical in this area, but it needs to be fuel resistant too. For now I'm
leaving the access panels off because it allows better access to install landing
gear hydraulic lines and wing wiring.
The finished project is
shown at right. For clarification, this shot is of the R/H spar, while the
prior shot (above it) is of the L/H spar. It took 28 hours of unplanned
construction time, but at least I didn't have to remove the spar from the
aircraft.
|